Projects
REAL PROJECTS.
Proven EXECUTION.

From Factory-Built Substations to Traditional construction, our project work reflects the planning, coordination, and experience behind every DTPS solution. Explore examples of how our team helps customers navigate complex scopes, demanding schedules, and critical power delivery needs.

Juniper Substation

A Factory-Built Approach to Grid Modernization

As energy demand continues to rise and aging infrastructure nears the end of its lifecycle, Utilities are rethinking their substation projects. The Juniper Substation project illustrates how DIS-TRAN Packaged Substations is helping accelerate that shift with a streamlined, Factory-Built solution that simplifies installation and reduces field exposure.

Manufactured and assembled at DIS-TRAN’s Project Support Services Facility, the 25kV skid weighed approximately 34,700 pounds and was built to include two breakers. Key components were integrated during assembly to reduce the time and labor required on-site, allowing the customer to focus on energizing the system rather than building it in the field.

What made this project especially noteworthy was its transport-ready configuration. Instead of requiring multiple truckloads, the base and top hat were engineered to fit together for shipment as a single, consolidated unit. This approach eliminated the need for numerous trucks and enabled a faster, more efficient installation process upon arrival.

For the customer, this project supported broader grid modernization goals while reducing field risk and improving schedule certainty. By shifting more of the work to a controlled environment, the team ensured consistent quality and minimized weather-related delays. It’s a strong example of how Factory-Built delivery methods can offer real advantages when speed, safety, and reliability matter most.

Caminada Substation

34.5kV Factory-Built Substation

Storm-Hardened Power for Coastal Resilience in Grand Isle, Louisiana

When Hurricane Ida struck Louisiana in 2021, the coastal community of Grand Isle,Louisiana faced catastrophic damage. More than 700 structures were destroyed, and over 2,500 were damaged—leaving residents without reliable power.

In the wake of that devastation, one thing was clear: resilience wasn't optional- it was essential.

That’s where DIS-TRAN Packaged Substations (DTPS) stepped in.

A Smarter, Stronger Solution

Our customer made the strategic decision to rebuild with infrastructure that could stand up to the next major storm. The solution: a Storm-Hardened, Factory-Built Substation (FBS) delivered by DTPS.

Key design features included:

  • 34.5kV Substation capacity
  • Elevated 20 feet above grade on a storm-rated steel platform
  • Engineered to withstand wind speeds up to 150 mph
  • Built and assembled off-site in a controlled environment

By manufacturing the substation at our facility and shipping it as a single integrated unit, we reduced on-site construction time, minimized risk in the field, and ensured consistent high-quality results from start to finish.

Built for the Future

The Caminada Substation stands as a powerful example of how Factory-Built, Storm-Hardened Substations can accelerate project timelines, increase safety on-site, and provide long-term resilience for coastal communities.

At DTPS, we’re proud to partner with utilities across the Gulf Coast and beyond—Changing the way Substations are Built and helping our customers find a better way.

Bridgeton Substation

How our first-ever double-decker substation delivered a first-rate experience for the client.

 

Factory-Built Substations (FBS) yield significant benefits, including time savings, cost efficiencies, and substantially reduced risk related to safety and project execution.

 

But is it still possible to preserve all of those benefits if the substation is so large it must be constructed in multiple segments, even in the factory? This project tested our ability to deliver all the advantages of FBS structures with a challenging design that would normally have compromised those gains.

 

Thankfully, we passed the test.

 

Specifically, this customer had never used a FBS before, and they were hoping to reap all the normal time and cost savings; but they also immediately threw us a curveball. They provided go-by drawings, but their preferred design specifications meant a structure larger than what we usually factory-build. That introduced expense and logistical challenges for shipping – in fact, as drawn, it might have been literally impossible to ship conventionally – and it would also mandate extra steps in the field to assemble.

 

The challenge was ensuring that the design would meet their requirements but still maximize all of the advantages of factory construction. To do so, we adapted the design to keep shipping costs low: ship it in two pieces and install one on top of the other as our first-ever  “double-decker” box structure substation.

 

It worked: the structure reached the site with no issues just when they wanted it, so we were able to preserve the speed and cost-of-transport advantages of the FBS. Then, even though field workers still had to attach the two pieces in the field, we made it easy, and  the structure took only about an hour to install. The FBS wins the day again!

 

The customer certainly thought so. After all was said and done, our first-time customer became an immediate repeat customer.

Valadez Substation

How a Factory-Built substation saved one utility from getting burned by a power outage.

Unanticipated risk is a specter that looms over utilities and their vendors, with the chance that a mishap could cause headaches for utilities and their customers always present.

 

This substation project proved how Factory-Built Substations(FBS) can offer a hedge against such risks.

 

It started like normal: the client ordered two four-bay FBS structures for their newest 12kV substation; however, they scheduled the project as if it were a traditional stick-built because they didn’t know how much time the Factory-Built approach would save. Spoiler: it saved a lot of time. In fact, the structures were built and installed so quickly, they completed the project an estimated 5 weeks early (taking 25 weeks instead of the planned30). The actual installation of the FBS itself took only a couple of hours, even though it was windy and rainy that day.

 

That’s the first example of how Factory-Built Substations can protect against risk. Building substations in the field exposes workers to potentially significant safety hazards, especially during inclement weather. Wind and elevation can be a lethal combination. But in this case, the substation structure was already constructed, so installation was just a matter of setting it in placeand affixing it to the foundation.

 

The second example is even more striking: a breaker explosion and subsequent fire at a substation down the road left 14,000customers without power, potentially for days. But because the new substation had been completed so far ahead of schedule, all the customer needed to do was bring in the transmission lines and quickly complete final steps to commissionthe station. The result: instead of losing power for days, customers had power restored within a matter of hours.

In their words: "We would've been in trouble if [this] substation [had not been] ready to go online.

Pike & Underwood Substation

Transcending national borders with seamless supply & transportation services that border on extraordinary.

The largest transmission company in Alberta, Canada wanted to expand the 230kV/138kV Pike Substation as part of the Christina Lake Area Transmission System Development initiative, and they needed a partner fluent in international substation supply. They turned to DIS-TRAN. While the scope of work was typical – the steel structures and everything that attaches to them – the job’s location in far northern Alberta, Canada, combined with a winter schedule, created a pressing set of challenges:

  • Customs: Since we had to cross the Canadian border, we took a greater role in managing shipments ourselves — we even sent trucks directly to a manufacturer to pick up materials!
  • Shipping: The job site was so far north, not even FedEx or UPS delivered. For smaller shipments, we found a reliable, independent Canadian shipping broker.
  • Winter: With work being completed in a Canadian winter, we had to plan tactically to ensure transportation deliveries would be able to weather the sometimes punishing conditions.
  • Standards: Equipment and project standards vary slightly from country to country, so we leveraged our existing network of suppliers, and found a few new ones, to meet every need.

In fact, not only did we get to flex our logistics and project management muscles by running a nearly frictionless project in an incredibly far-flung location, we were also able to forge new relationships and cement existing ones, all while meeting every substation spec down to the nuts and bolts.

Poker Lake Substation

Miles into the middle of nowhere, DIS-TRAN makes a first-class first-impression…and potentially saves our client eight figures annually.

Home to a scant 27,000 people – fewer people than would fit into a football stadium – Carlsbad, NM is surrounded by miles and miles of empty, remote land. It’s the perfect region for a drilling operation run by our customer (part of the Bass Oil Group), but the area’s aging transmission lines required them to power the operation with inefficient and expensive diesel engines. They realized they could unearth significant savings by building an on-site, 115kV/12.47kV outdoor steel substation (and updating the local transmission lines in the process).

They were right: we estimate that for every $1 spent on building the substation, they saved $3 to $6 in annual energy, operations, maintenance and fuel costs over the previous installation.

They asked for the full-service experience from DIS-TRAN, so under our EPC arrangement, we coordinated all aspects of the substation design and construction, including overseeing and liaising between the electrical contractor; DIS-TRAN’s own engineering, procurement and billing teams; and our customer's staff and stakeholders. We even deployed advanced services to ensure the client and contractors faced few-to-no issues during construction and installation. For example, our on-site inventory services team personally delivered secure Connex containers with all project materials and then tallied and measured all equipment and supplies against project needs.

In short, we delivered end-to-end, top-to-bottom, first-class service that saw the substation energized on time and completed with such rigorous adherence to the intricate design that the staff in Ft. Worth, TX can monitor station performance down to individual relays.

The customer was so pleased they brought us their next project without seeking even a single outside bid!

Erath Substation

We designed a storm-hardening solution that blows the others out of the water.

Storm surge and flooding are major concerns that all coastal utilities must weather. According to our own local utility (Entergy), the Gulf Coast alone is facing cumulative damages of $350B over the next 20 years from hurricanes and severe storms.

In the aftermath of devastation from Hurricanes Katrina, Ike, Gustav and Rita, one customer wanted to insulate their substation against further flood damage.

DIS-TRAN innovated a brand new solution: in-place elevation. We elevated the flood-sensitive equipment of an existing 115-24.5kV outdoor open-air substation, including:

  • Four 115kV circuit switcher electronic control cabinets
  • Two 33MVA 115-25kV power transformers
  • Two 25kV distribution substation structures with associated circuit breakers
  • One control building

We lifted the equipment to 13 feet above mean sea level, and we did so with:

  • No change in power station performance or system reliability permitted
  • No appreciable change in operational and maintenance practices permitted
  • No service disruption throughout the life of the project permitted
  • No increase in construction safety risk permitted
  • No budget overages
  • No schedule delays

Marigold Substation

We collapsed installation to just days with a tactic worth its weight in gold.

Our customer – a gold mine in northern Nevada – had upgraded its enormous power shovel and thus needed to update its 115/24.9kV substation. But with the remote site located deep in the Nevada desert, two hours from the nearest urban center, it was key to keep on-site construction to a bare minimum. By shipping pre-assembled, skid-mounted equipment, DIS-TRAN reduced installation time to days.

The client asked DIS-TRAN to produce the nine requested low-side distribution bays as assembled as possible at delivery. DIS-TRAN’s engineers mined their deep expertise and found a solution: dividing the equipment into three different sections, three bays apiece, and mounting each section onto skids for easy transport and installation. The skid-mounted assemblies were kept slim to slide onto standard trucks, split into top-and-bottom halves to undercut height restrictions, and still managed to meet performance specs perfectly.

The trucks arrived on-site Monday morning, and by noon on Tuesday, we had the complete low-side distribution section (all nine bays) sitting in place on their foundations. According to our customers – both the mine’s owner and their engineering firm – DIS-TRAN struck gold. We’ve since gone on to do more work for the same contacts from both companies.

Orrington Substation

Building a lattice-type tower on the double!

Our customer, a public utility based in the Northeast, wanted to build a new 115kV add-on to an existing 345kv substation. This project meant duplicating some of the existing structures right next to where the existing steel was standing; the biggest challenge was perfectly replicating an entire lattice-type tower.

It was a complex build, as the lattices supported an extensive array of equipment, from disconnect switches to instrument transformers. DIS-TRAN’s engineers gave the project extra care and time to ensure the new tower would both perfectly match the aesthetics of the existing one and also meet the new specs and functionality requirements.

With a high-quality design in place, DIS-TRAN was able to deliver the project and meet the customer’s scheduling requirements. In fact, we did so even after running into a hiccup (a shipment of mis-fabricated steel, which we got re-delivered within a week)!

The client was so pleased they sent us some homemade jelly and three more substations projects just like Orrington!

East Fishkill Substation

We cut nearly 50% from project time to meet an “impossible” schedule.

This customer hired DIS-TRAN to tie two yards together with a new line, with the project scope including a breaker, some bus supports and a new switch. Pretty easy, right? Not so fast: the job came with a couple of serious provisos:

  • The customer was working on an incredibly accelerated (other companies might say “impossible”) schedule.
  • The line boasted an unusually high fault current of 63kA, mandating special requirements in supporting the bus bar.

This was a difficult job, no doubt, but we were able to hit the ground running. We pushed some vendors, worked some extra hours, and poured some creativity into solving the engineering challenges. For example, DIS-TRAN’s substation engineers developed a unique double “inverted V” insulator design, pictured above, to account for the fault current loadings. With this design, we could furnish readily available insulators manufactured domestically as opposed to waiting on custom-designed, special insulators manufactured overseas. That cut project lead time right away.

The result: DIS-TRAN pulled the project together in 12 weeks instead of the normal 20. And that’s with no shortcuts, per specs, per code.

Lakeside II Substation

DIS-TRAN rises to the challenge, so our customer (a contractor) can fly high.

In this 345kV station project, DIS-TRAN worked hard to make our customer (a billion-dollar engineering contractor) look good to their customer (a major utility that kept rolling out challenging design changes).

In addition to our standard scope of work (the steel structures and everything that attaches to them), this project also required engineering and design work on overhead transmission lines connecting the substation to a nearby steel mill. That created a looming obstacle: how to deliver enormous 120-foot transmission poles cross-country, timed for delivery in-step with the end-user's construction schedule, with a rising tide of design changes flying our way. Oh, and we had to get everything in place before the end of a scheduled outage.

DIS-TRAN rose to the occasion. We carefully connected and coordinated all of the teams, vendors and schedules for a seamless workflow. The high point? Our organization and efficiency made our customer shine in front of theirs.

Carver Substation

DIS-TRAN turns mountains into molehills with skid-mounted substations.

The utility requested an innovative solution to an age-old problem: time. Specifically, how could we offset their lengthy permitting process?

Difficult but doable: DIS-TRAN delivered designs and materials to our partner contractor to pre-assemble substation structures and mount them onto skids while the end-user utility awaited permits. By the time permitting was done and the actual job-site opened, the equipment was already assembled and mounted for transport. Instead of facing a mountain of work awaiting them, the contractor and utility were able to start installing everything right then and there.

This approach saved more than just enormous time in the yard: the skids also reduced the number of foundations needed.

Rosamund Substation

Three or four weeks to install? Try 4 days.

DIS-TRAN gave this customer two options for their substation project: pre-assembled skid-mounted or traditional "stick-built."

They went with skids. DIS-TRAN fully marshaled the project (with the steel built just across the street by our sister company, DIS-TRAN Steel), so we gathered all materials in our warehouse and assembled the equipment there, then mounted everything onto the skids for shipping.

The subsequent 1,700-mile cross-country journey to the job-site was a breeze. Our engineering and logistics teams worked hand-in-glove from day one to ensure the assembled equipment could ultimately go on the truck safely, with no permits or re-routing required. (That saved half the typical cost and time of shipping right there.) Then, once the equipment arrived on site, all they had to do was grab it with cranes, set in place and bolt down.

An installation that would have taken three to four weeks with a traditional approach took just four days with DIS-TRAN's.

Keene Road Substation

The DIS-TRAN PFB enables substations projects to weather temperamental conditions.

Weather always has an enormous impact on substation construction: as difficulties and added expenses deluge laborers, and safety and scheduling issues turn stormy, environmental conditions can leave projects out in the cold.

And winter weather is among the most temperamental. That’s why DIS-TRAN is always developing better ways to mitigate the impact of outside factors, as with our pre-fabricated bus. The DIS-TRAN PFB is a complete bus assembly whose final installation requires little-to-no field welding.

On this project, we provided a 345kV PFB for a substation serving as an interconnect between a wind energy project and a transmission system.

And we installed it effortlessly, even in the middle of a blustery winter.It arrived on site factory-assembled, ready to simply be dropped into place.

Exactly the reason we invented the PFB.

Copper Ridge Factory-Built Substation

DIS-TRAN made quick work of our largest ever (to date) factory-built substation.

The power of a DIS-TRAN factory-built substation is time: by speedily assembling a complete system in a factory setting, we can drive down total installed costs and massively reduce on-site work time and expense.

Such was the case with our biggest factory-built station to date. We were able to build a 40-foot-long, 18-foot-wide, 18,000-pound 12kV substation inside DIS-TRAN’s project support service center … in just 3 weeks!

Then, upon arrival onsite in a single piece, the equipment took just 30 minutes to unload and bolt into place.

The result was a station that was easily energized “on schedule and under budget,” according to the customer, who also reported that they “saw a huge decrease in labor hours to finish that part of the station.

”The whole DIS-TRAN part of the installation was completed within a week of delivery.

TNMP 15kV Factory-Built Substation

DIS-TRAN’s factory-built substation means installation in a day, even for remote locations.

Serving more than 9,000 miles of transmission and distribution lines to provide more than 243,000 homes and businesses in more than 70 communities throughout Texas, and facing significant retail customer growth, Texas-New Mexico Power (TNMP) [RG1] needed to convert a large part of its system in west Texas from 69kV to 138kV.

They came to DIS-TRAN for our factory-built substation, which would help them shorten the schedule and minimize the difficulties of working in such a remote location.

It worked: Chris Gerety, Director of Engineering and Land Services for TNMP, says having the distribution bay factory-built possibly shaved two to three months off their total construction time.

Joe Sandifer, a safety inspector for TechServ who worked on-site for TNMP’s project, agrees. He estimates that a substation that size, erected solely in the field, would typically take weeks to construct, at least. In other words, an installation starting on March 22 would take until early May or later, whereas DIS-TRAN’s installation both started and finished on March 22. Sandifer’s reaction: “I had never seen anything like that before. We always have had to do everything on the job site. It was perfect.”

Based on Gerety’s assessment, given the elimination of material shortages, eradication of alignment issues, and the removal of weather delays, we conservatively estimate that TNMP saw a construction labor savings of $60,000 to $80,000.

TNMP was certainly pleased with the project: “We had a really positive experience and the project was very favorable on our side,” says Gerety.

For an in-depth technical analysis of this project, read our paper “Saving Time and Money: A Case Study of a Texas Utility’s Experience Utilizing A Customized Factory-Built Substation Approach for its Standard Outdoor Open-Air Distribution Substation.”

In 2016, TSDOS (Transmission and Substation Design and Operation Symposium) selected DIS-TRAN Packaged Substations to present a case study on this project. You can watch the presentation by clicking the video link below.

Kelson Ridge

230kV Substation for a Steam Generation Power Plant

Unusual complexities in project management didn’t stop us from keeping this project moving full steam ahead.

The customer wanted to kick the substation’s power up to 230kV in this big project, and they retained DIS-TRAN for a typical packaged substation with a very atypical change: they handled the supply of some major equipment themselves.

Since we usually handle this aspect of projects, DIS-TRAN and Project Manager Tim Powell had to engage in more complicated coordination efforts than normal with multiple organizations and third parties. “It required a lot of interaction between the involved parties,” says Powell, but he said DIS-TRAN’s normal adaptiveness was easily up to the challenge. “Some adjustment was needed, but nothing that we’re not used to.”

Additionally, separate parts of the facility were controlled by different entities: the switchyard was governed by the project owner (and had to adhere to their very strict drawing and engineering standards) while the transmission line belonged to the engineering company, whose design mandates were more flexible.

Transmission Line Packaging

DIS-TRAN’s transmission line packaging is top of the line service.

It was a completely new type of project for us: in addition to a standard substation construction project, the customer was rebuilding a 5- to a 10-mile length of transmission lines in rural New England. We agreed to procure and package all materials for each power line pole along that stretch.

We packed all the necessary materials and components into a single big crate for each transmission pole, which enabled us to transport and deposit each crate exactly where the pole or tower would be erected.

This approach spared the field crews from having to make back-and-forth trips to gather the equipment themselves and drive everything out to the construction sites, some of which were extremely remote in mountainous and rural terrain. Then, once on site, field crews could quickly raise each pole, connect it to the system, and move on right away to the next site.

Our exhaustive QC process also helped reduce overall error in the materials by catching and correcting any discrepancies between what was ordered, what was needed, and what was included before shipment.

PFB & Packaging

DIS-TRAN’s efficiency was so striking, it set new protocols for both our and the customer’s projects.

Large projects can mean a lot of field welding, adding time and expense to already strained budgets and schedules. For example, if this huge 230/34.5kV project had required full welding out in the field, it might have taken upwards of a month to complete that part of the project.

That’s exactly the situation DIS-TRAN’s pre-fabricated bus (PFB) is designed to alleviate. Even with a sectional approach to installation (where the client moved back-and-forth between project pieces, instead of installing the PFB all at once), we were still able to cut that welding time at least in half.

We further streamlined the project with our approach to packaging for this customer.

Specifically, instead of layering jumpers and other materials on top of each other in huge crates, we stood them up vertically, tagged them, and separated them into partitions. We then divided components into dedicated crates for each transformer. That way, the clients could:

  1. Place each crate exactly where it would be used,
  2. Verify at a glance that all materials were present, and
  3. Pull out exactly what they needed, when they needed it.  

In fact, this project was so successfully efficient, it set new standards in practices both at DIS-TRAN and with the customer. We have since adapted this approach to packaging materials for all projects, and the client was so pleased with the PFB, we now quote our PFB product on all their projects.

Field Welding

DIS-TRAN’s certified welders are equally at home in our shop and in the field.

DIS-TRAN’s pre-fabricated bus (PFB) can significantly reduce necessary field welds because most of the welding happens during fabrication before the PFB even arrives on site. That, in turn, yields shorter lead times, reduced expenses, and safer projects.

However, even the PFB rarely eliminates all field welding. For example, some structures may be too big to ship completely welded, as happened on this 138kV substation. Here, we handled most of the welding in our assembly facility but still had 56 welds left to be completed in the field.

Although the customer had welders on staff, none felt comfortable working with aluminum. Thankfully, DIS-TRAN’s staff of welders, including our shop manager, are seasoned and certified workers who excel equally both in the shop and in the field.

Levi Deleon, DIS-TRAN Project Manager, explains, “We try to eliminate field welding for the customer as much as possible. When paired with the PFB, DIS-TRAN has the right people to provide that service and do it very well and very efficiently.”

In fact, schedule-wise, if DIS-TRAN follows the PFB with our own field welding service, we can ensure work is completed immediately after delivery of the PFB. That yields significant scheduling efficiencies – which, in turn, make the service more cost advantageous.

Juniper Substation

A Factory-Built Approach to Grid Modernization

As energy demand continues to rise and aging infrastructure nears the end of its lifecycle, Utilities are rethinking their substation projects. The Juniper Substation project illustrates how DIS-TRAN Packaged Substations is helping accelerate that shift with a streamlined, Factory-Built solution that simplifies installation and reduces field exposure.

Manufactured and assembled at DIS-TRAN’s Project Support Services Facility, the 25kV skid weighed approximately 34,700 pounds and was built to include two breakers. Key components were integrated during assembly to reduce the time and labor required on-site, allowing the customer to focus on energizing the system rather than building it in the field.

What made this project especially noteworthy was its transport-ready configuration. Instead of requiring multiple truckloads, the base and top hat were engineered to fit together for shipment as a single, consolidated unit. This approach eliminated the need for numerous trucks and enabled a faster, more efficient installation process upon arrival.

For the customer, this project supported broader grid modernization goals while reducing field risk and improving schedule certainty. By shifting more of the work to a controlled environment, the team ensured consistent quality and minimized weather-related delays. It’s a strong example of how Factory-Built delivery methods can offer real advantages when speed, safety, and reliability matter most.

Caminada Substation

34.5kV Factory-Built Substation

Storm-Hardened Power for Coastal Resilience in Grand Isle, Louisiana

When Hurricane Ida struck Louisiana in 2021, the coastal community of Grand Isle,Louisiana faced catastrophic damage. More than 700 structures were destroyed, and over 2,500 were damaged—leaving residents without reliable power.

In the wake of that devastation, one thing was clear: resilience wasn't optional- it was essential.

That’s where DIS-TRAN Packaged Substations (DTPS) stepped in.

A Smarter, Stronger Solution

Our customer made the strategic decision to rebuild with infrastructure that could stand up to the next major storm. The solution: a Storm-Hardened, Factory-Built Substation (FBS) delivered by DTPS.

Key design features included:

  • 34.5kV Substation capacity
  • Elevated 20 feet above grade on a storm-rated steel platform
  • Engineered to withstand wind speeds up to 150 mph
  • Built and assembled off-site in a controlled environment

By manufacturing the substation at our facility and shipping it as a single integrated unit, we reduced on-site construction time, minimized risk in the field, and ensured consistent high-quality results from start to finish.

Built for the Future

The Caminada Substation stands as a powerful example of how Factory-Built, Storm-Hardened Substations can accelerate project timelines, increase safety on-site, and provide long-term resilience for coastal communities.

At DTPS, we’re proud to partner with utilities across the Gulf Coast and beyond—Changing the way Substations are Built and helping our customers find a better way.

Bridgeton Substation

How our first-ever double-decker substation delivered a first-rate experience for the client.

 

Factory-Built Substations (FBS) yield significant benefits, including time savings, cost efficiencies, and substantially reduced risk related to safety and project execution.

 

But is it still possible to preserve all of those benefits if the substation is so large it must be constructed in multiple segments, even in the factory? This project tested our ability to deliver all the advantages of FBS structures with a challenging design that would normally have compromised those gains.

 

Thankfully, we passed the test.

 

Specifically, this customer had never used a FBS before, and they were hoping to reap all the normal time and cost savings; but they also immediately threw us a curveball. They provided go-by drawings, but their preferred design specifications meant a structure larger than what we usually factory-build. That introduced expense and logistical challenges for shipping – in fact, as drawn, it might have been literally impossible to ship conventionally – and it would also mandate extra steps in the field to assemble.

 

The challenge was ensuring that the design would meet their requirements but still maximize all of the advantages of factory construction. To do so, we adapted the design to keep shipping costs low: ship it in two pieces and install one on top of the other as our first-ever  “double-decker” box structure substation.

 

It worked: the structure reached the site with no issues just when they wanted it, so we were able to preserve the speed and cost-of-transport advantages of the FBS. Then, even though field workers still had to attach the two pieces in the field, we made it easy, and  the structure took only about an hour to install. The FBS wins the day again!

 

The customer certainly thought so. After all was said and done, our first-time customer became an immediate repeat customer.

Valadez Substation

How a Factory-Built substation saved one utility from getting burned by a power outage.

Unanticipated risk is a specter that looms over utilities and their vendors, with the chance that a mishap could cause headaches for utilities and their customers always present.

 

This substation project proved how Factory-Built Substations(FBS) can offer a hedge against such risks.

 

It started like normal: the client ordered two four-bay FBS structures for their newest 12kV substation; however, they scheduled the project as if it were a traditional stick-built because they didn’t know how much time the Factory-Built approach would save. Spoiler: it saved a lot of time. In fact, the structures were built and installed so quickly, they completed the project an estimated 5 weeks early (taking 25 weeks instead of the planned30). The actual installation of the FBS itself took only a couple of hours, even though it was windy and rainy that day.

 

That’s the first example of how Factory-Built Substations can protect against risk. Building substations in the field exposes workers to potentially significant safety hazards, especially during inclement weather. Wind and elevation can be a lethal combination. But in this case, the substation structure was already constructed, so installation was just a matter of setting it in placeand affixing it to the foundation.

 

The second example is even more striking: a breaker explosion and subsequent fire at a substation down the road left 14,000customers without power, potentially for days. But because the new substation had been completed so far ahead of schedule, all the customer needed to do was bring in the transmission lines and quickly complete final steps to commissionthe station. The result: instead of losing power for days, customers had power restored within a matter of hours.

In their words: "We would've been in trouble if [this] substation [had not been] ready to go online.

Poker Lake Substation

Miles into the middle of nowhere, DIS-TRAN makes a first-class first-impression…and potentially saves our client eight figures annually.

Home to a scant 27,000 people – fewer people than would fit into a football stadium – Carlsbad, NM is surrounded by miles and miles of empty, remote land. It’s the perfect region for a drilling operation run by our customer (part of the Bass Oil Group), but the area’s aging transmission lines required them to power the operation with inefficient and expensive diesel engines. They realized they could unearth significant savings by building an on-site, 115kV/12.47kV outdoor steel substation (and updating the local transmission lines in the process).

They were right: we estimate that for every $1 spent on building the substation, they saved $3 to $6 in annual energy, operations, maintenance and fuel costs over the previous installation.

They asked for the full-service experience from DIS-TRAN, so under our EPC arrangement, we coordinated all aspects of the substation design and construction, including overseeing and liaising between the electrical contractor; DIS-TRAN’s own engineering, procurement and billing teams; and our customer's staff and stakeholders. We even deployed advanced services to ensure the client and contractors faced few-to-no issues during construction and installation. For example, our on-site inventory services team personally delivered secure Connex containers with all project materials and then tallied and measured all equipment and supplies against project needs.

In short, we delivered end-to-end, top-to-bottom, first-class service that saw the substation energized on time and completed with such rigorous adherence to the intricate design that the staff in Ft. Worth, TX can monitor station performance down to individual relays.

The customer was so pleased they brought us their next project without seeking even a single outside bid!

Orrington Substation

Building a lattice-type tower on the double!

Our customer, a public utility based in the Northeast, wanted to build a new 115kV add-on to an existing 345kv substation. This project meant duplicating some of the existing structures right next to where the existing steel was standing; the biggest challenge was perfectly replicating an entire lattice-type tower.

It was a complex build, as the lattices supported an extensive array of equipment, from disconnect switches to instrument transformers. DIS-TRAN’s engineers gave the project extra care and time to ensure the new tower would both perfectly match the aesthetics of the existing one and also meet the new specs and functionality requirements.

With a high-quality design in place, DIS-TRAN was able to deliver the project and meet the customer’s scheduling requirements. In fact, we did so even after running into a hiccup (a shipment of mis-fabricated steel, which we got re-delivered within a week)!

The client was so pleased they sent us some homemade jelly and three more substations projects just like Orrington!

Rosamund Substation

Three or four weeks to install? Try 4 days.

DIS-TRAN gave this customer two options for their substation project: pre-assembled skid-mounted or traditional "stick-built."

They went with skids. DIS-TRAN fully marshaled the project (with the steel built just across the street by our sister company, DIS-TRAN Steel), so we gathered all materials in our warehouse and assembled the equipment there, then mounted everything onto the skids for shipping.

The subsequent 1,700-mile cross-country journey to the job-site was a breeze. Our engineering and logistics teams worked hand-in-glove from day one to ensure the assembled equipment could ultimately go on the truck safely, with no permits or re-routing required. (That saved half the typical cost and time of shipping right there.) Then, once the equipment arrived on site, all they had to do was grab it with cranes, set in place and bolt down.

An installation that would have taken three to four weeks with a traditional approach took just four days with DIS-TRAN's.

Copper Ridge Factory-Built Substation

DIS-TRAN made quick work of our largest ever (to date) factory-built substation.

The power of a DIS-TRAN factory-built substation is time: by speedily assembling a complete system in a factory setting, we can drive down total installed costs and massively reduce on-site work time and expense.

Such was the case with our biggest factory-built station to date. We were able to build a 40-foot-long, 18-foot-wide, 18,000-pound 12kV substation inside DIS-TRAN’s project support service center … in just 3 weeks!

Then, upon arrival onsite in a single piece, the equipment took just 30 minutes to unload and bolt into place.

The result was a station that was easily energized “on schedule and under budget,” according to the customer, who also reported that they “saw a huge decrease in labor hours to finish that part of the station.

”The whole DIS-TRAN part of the installation was completed within a week of delivery.

Pike & Underwood Substation

Transcending national borders with seamless supply & transportation services that border on extraordinary.

The largest transmission company in Alberta, Canada wanted to expand the 230kV/138kV Pike Substation as part of the Christina Lake Area Transmission System Development initiative, and they needed a partner fluent in international substation supply. They turned to DIS-TRAN. While the scope of work was typical – the steel structures and everything that attaches to them – the job’s location in far northern Alberta, Canada, combined with a winter schedule, created a pressing set of challenges:

  • Customs: Since we had to cross the Canadian border, we took a greater role in managing shipments ourselves — we even sent trucks directly to a manufacturer to pick up materials!
  • Shipping: The job site was so far north, not even FedEx or UPS delivered. For smaller shipments, we found a reliable, independent Canadian shipping broker.
  • Winter: With work being completed in a Canadian winter, we had to plan tactically to ensure transportation deliveries would be able to weather the sometimes punishing conditions.
  • Standards: Equipment and project standards vary slightly from country to country, so we leveraged our existing network of suppliers, and found a few new ones, to meet every need.

In fact, not only did we get to flex our logistics and project management muscles by running a nearly frictionless project in an incredibly far-flung location, we were also able to forge new relationships and cement existing ones, all while meeting every substation spec down to the nuts and bolts.

Marigold Substation

We collapsed installation to just days with a tactic worth its weight in gold.

Our customer – a gold mine in northern Nevada – had upgraded its enormous power shovel and thus needed to update its 115/24.9kV substation. But with the remote site located deep in the Nevada desert, two hours from the nearest urban center, it was key to keep on-site construction to a bare minimum. By shipping pre-assembled, skid-mounted equipment, DIS-TRAN reduced installation time to days.

The client asked DIS-TRAN to produce the nine requested low-side distribution bays as assembled as possible at delivery. DIS-TRAN’s engineers mined their deep expertise and found a solution: dividing the equipment into three different sections, three bays apiece, and mounting each section onto skids for easy transport and installation. The skid-mounted assemblies were kept slim to slide onto standard trucks, split into top-and-bottom halves to undercut height restrictions, and still managed to meet performance specs perfectly.

The trucks arrived on-site Monday morning, and by noon on Tuesday, we had the complete low-side distribution section (all nine bays) sitting in place on their foundations. According to our customers – both the mine’s owner and their engineering firm – DIS-TRAN struck gold. We’ve since gone on to do more work for the same contacts from both companies.

Carver Substation

DIS-TRAN turns mountains into molehills with skid-mounted substations.

The utility requested an innovative solution to an age-old problem: time. Specifically, how could we offset their lengthy permitting process?

Difficult but doable: DIS-TRAN delivered designs and materials to our partner contractor to pre-assemble substation structures and mount them onto skids while the end-user utility awaited permits. By the time permitting was done and the actual job-site opened, the equipment was already assembled and mounted for transport. Instead of facing a mountain of work awaiting them, the contractor and utility were able to start installing everything right then and there.

This approach saved more than just enormous time in the yard: the skids also reduced the number of foundations needed.

Transmission Line Packaging

DIS-TRAN’s transmission line packaging is top of the line service.

It was a completely new type of project for us: in addition to a standard substation construction project, the customer was rebuilding a 5- to a 10-mile length of transmission lines in rural New England. We agreed to procure and package all materials for each power line pole along that stretch.

We packed all the necessary materials and components into a single big crate for each transmission pole, which enabled us to transport and deposit each crate exactly where the pole or tower would be erected.

This approach spared the field crews from having to make back-and-forth trips to gather the equipment themselves and drive everything out to the construction sites, some of which were extremely remote in mountainous and rural terrain. Then, once on site, field crews could quickly raise each pole, connect it to the system, and move on right away to the next site.

Our exhaustive QC process also helped reduce overall error in the materials by catching and correcting any discrepancies between what was ordered, what was needed, and what was included before shipment.

Caminada Substation

34.5kV Factory-Built Substation

Storm-Hardened Power for Coastal Resilience in Grand Isle, Louisiana

When Hurricane Ida struck Louisiana in 2021, the coastal community of Grand Isle,Louisiana faced catastrophic damage. More than 700 structures were destroyed, and over 2,500 were damaged—leaving residents without reliable power.

In the wake of that devastation, one thing was clear: resilience wasn't optional- it was essential.

That’s where DIS-TRAN Packaged Substations (DTPS) stepped in.

A Smarter, Stronger Solution

Our customer made the strategic decision to rebuild with infrastructure that could stand up to the next major storm. The solution: a Storm-Hardened, Factory-Built Substation (FBS) delivered by DTPS.

Key design features included:

  • 34.5kV Substation capacity
  • Elevated 20 feet above grade on a storm-rated steel platform
  • Engineered to withstand wind speeds up to 150 mph
  • Built and assembled off-site in a controlled environment

By manufacturing the substation at our facility and shipping it as a single integrated unit, we reduced on-site construction time, minimized risk in the field, and ensured consistent high-quality results from start to finish.

Built for the Future

The Caminada Substation stands as a powerful example of how Factory-Built, Storm-Hardened Substations can accelerate project timelines, increase safety on-site, and provide long-term resilience for coastal communities.

At DTPS, we’re proud to partner with utilities across the Gulf Coast and beyond—Changing the way Substations are Built and helping our customers find a better way.

Erath Substation

We designed a storm-hardening solution that blows the others out of the water.

Storm surge and flooding are major concerns that all coastal utilities must weather. According to our own local utility (Entergy), the Gulf Coast alone is facing cumulative damages of $350B over the next 20 years from hurricanes and severe storms.

In the aftermath of devastation from Hurricanes Katrina, Ike, Gustav and Rita, one customer wanted to insulate their substation against further flood damage.

DIS-TRAN innovated a brand new solution: in-place elevation. We elevated the flood-sensitive equipment of an existing 115-24.5kV outdoor open-air substation, including:

  • Four 115kV circuit switcher electronic control cabinets
  • Two 33MVA 115-25kV power transformers
  • Two 25kV distribution substation structures with associated circuit breakers
  • One control building

We lifted the equipment to 13 feet above mean sea level, and we did so with:

  • No change in power station performance or system reliability permitted
  • No appreciable change in operational and maintenance practices permitted
  • No service disruption throughout the life of the project permitted
  • No increase in construction safety risk permitted
  • No budget overages
  • No schedule delays
where tradition
meets innovation

Decades of experience. Two proven approaches. One team focused on delivering your project the right way.

At DIS-TRAN Packaged Substations, we bring together the strength of Traditional construction and the efficiency of Factory-Built solutions, helping you navigate complexity, reduce uncertainty, and keep your project movingforward. Whether your project calls for a field-executed approach or a controlled, offsite build, our team works alongside yours to plan, coordinate, and execute with discipline from start to finish.

Thank you

Your submission has been received!
We can't wait to get started on your project.
Oops! Something went wrong while submitting the form.