As energy demand continues to rise and aging infrastructure nears the end of its lifecycle, Utilities are rethinking their substation projects. The Juniper Substation project illustrates how DIS-TRAN Packaged Substations is helping accelerate that shift with a streamlined, Factory-Built solution that simplifies installation and reduces field exposure.
Manufactured and assembled at DIS-TRAN’s Project Support Services Facility, the 25kV skid weighed approximately 34,700 pounds and was built to include two breakers. Key components were integrated during assembly to reduce the time and labor required on-site, allowing the customer to focus on energizing the system rather than building it in the field.
What made this project especially noteworthy was its transport-ready configuration. Instead of requiring multiple truckloads, the base and top hat were engineered to fit together for shipment as a single, consolidated unit. This approach eliminated the need for numerous trucks and enabled a faster, more efficient installation process upon arrival.
For the customer, this project supported broader grid modernization goals while reducing field risk and improving schedule certainty. By shifting more of the work to a controlled environment, the team ensured consistent quality and minimized weather-related delays. It’s a strong example of how Factory-Built delivery methods can offer real advantages when speed, safety, and reliability matter most.